Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 63

October 8 - October 15, 2017

Week 63
In Week 63 we find ourselves 5 weeks before Dedication. This week our church found Her voice when our organ returned. Carpet was laid in the Sacristy, choir area and confessional. Construction cleaning completed In Week 64 our pews will be delivered and installed which may go into Week 65. Outside should see the installation of a backup generator and a level grade all around with top soil in preparation for sprinkler installation in Week 65.

No more videos or pictures. Don't want to spoil the surprise. See you November 18th for the Dedication.

Week 63 - Accomplishments

  • Organ delivered and installed.
  • Construction cleaning complete.
  • Carpet installed.

Week 64 - Goal

  • Pew installation.
  • Install Bell system.
  • Grade outside in preparation for sprinklers.