CHURCH RENOVATION

PHOTOS - WEEK 62

October 1 - October 7, 2017

Week 62

In Week 62 Church Interiors finished the artwork over the High Altar, the Mary and Joseph Shrines, embellishment of the large medallions on the ceiling and so much more.  Our project is coming to a quick end and it's looking more and more like a House of God. Outside we are knee deep in top soil and ready to begin landscaping over the next 3 weeks.

From keying our doors to match our current key-master to completing the confessional, programming lighting "scenes" to sound testing and beginning construction cleaning, Week 63 will go fast and furious.

No more videos or pictures.  Don't want to spoil the surprise.  See you November 18th for the Dedication.

Week 62 - Accomplishments

  • Decorative / Artistic work complete
  • Top soil delivered.

Week 63 - Goal

  • Install backup generator.
  • Install carpeting in Sacristy.
  • Begin Landscaping
  • Begin construction cleaning.