Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 59

September 10 - September 16, 2017

WEEK  59

We received a special delivery in Week 59.  Church Interiors delivered all the Sanctuary furniture as well as the decorative embellishments for the front and rear shrines.  They will begin their work in Week 60.   We should also see the completion of all floor tile work as well as any ceiling touch up.

Also in Week 60 we'll see a lot of work outside with the sidewalks and front patio formed and poured. During the next 5 weeks we'll see it all come together with the installation of the sound and organ systems, decorative artwork and embellishments, and... pews and our stained glass windows.

Week 59 - Accomplishments

  • Floor tile complete on North side and continuing.
  • Sanctuary furniture delivered
  • Begin sidewalk framing

Week 60 - Goal

  • Complete floor tile.
  • Form exterior sidewalks.
  • Begin Decorative / Artistic work.
  • Install security cameras.