Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 57

August 27 - September 2, 2017

WEEK  57

In Week 57 we began tiling the floor in the addition now that the ceiling is complete and the scaffolding has been removed.  All interior lighting fixtures have been installed.  Outside, drain lines for the rain gutters were installed and the construction trailer was removed.  In Week 58 we should see sidewalk forms go up and continuation of tiling and trim work inside.

Week 57– Accomplishments

  • All interior lighting fixtures installed
  • Construction trailer removed.
  • Floor tiling of addition begins.

Week 58 – Goal

  • Remove interior lift and scaffolding.
  • Form exterior sidewalks.
  • Continue floor tiling.

Click the Image Below for all the Photos from This Week.