Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 53

July 30 - August 5, 2017

WEEK  53

In Week 53 staining of the woodwork has begun with paining scheduled to follow behind the staining.  The parking lot is very near completion with the striping complete and signage set for next week.  Work is wrapping up with the tower with a new floor (which is really a roof) being installed.  Week 54 should see the installation of the railings on the north and south side of the tower. 

Week 54 will also see sidewalk forming and more light fixtures.

Check out our lengthy “Project Tour – Week 53” video on our website.

Week 53 – Accomplishments

  • Striping of parking lot complete.
  • Continue with finish carpentry work

 

Week 54 – Goal

  • Parking lot signage.
  • Complete bell tower
  • Continue staining /painting