Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 52

July 23 - July 29, 2017

WEEK  52

In Week 52 we continue with the detail work of carpentry and tiling for the floor and ceiling.  Now that the high outside work is nearing completion we can begin grading and forming for sidewalks and lighting fixtures.  In week 53 we should see sidewalks poured and the completion of the Bell Tower and begin installation of sound and organ wiring.

Check out our lengthy “Project Tour – Week 52” video on our website.

Week 52 – Accomplishments

  • Backfill of curbing in parking lot.
  • Complete Mary/Joseph shrine tile work.
  • Continue with finish carpentry work
  • Gutters and soffits complete.

Week 53 – Goal

  • Complete Sanctuary tile.
  • Continue with ceiling and floor tiles.
  • Begin staining /painting

Click the Image Below for all the Photos from This Week.