Week 44 was continuing to drywall, tape or paint. The ceiling is complete for drywall and painting has begun. The 2 side “hobbit” doors have been sent out for re-finishing. Walls have been complete in the basement for the electrical, mechanical and water rooms. Week 45 will be more painting and finish work as well as installation of cabinets and plumbing fixtures.
See our Campaign Board in the Berst Hall lobby (East entrance) to see the latest pictures.

Week 44 – Accomplishments

• Complete drywall ceiling.
• Basement walls complete.

Week 45 – Goal

• Complete drywall ceiling over Altar.
• Continue painting.
• Begin Altar platform.
• Install cabinets.