Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 41

May 7 - May 13, 2017

Week 41

It was a flurry of activity in week 41.  Most of the drywall has been installed on all the walls with taping nearly complete.  Floor and wall tiling has been completed in the restrooms.  New framing has been installed on the flat part of the ceiling in the old section to receive drywall next week. 

I will be on vacation for the next 2 weeks so there will be no articles until week 44.  But in the next 2 weeks all drywall work for walls and ceiling should be complete and ready for paint.  Floor tiling will begin at the w est end of the church working east toward the new section.  The Altar platform and ramps should be built and we may even see painting begin.  And if the weather cooperates we may even see activity in the parking lot.

Week 41 – Accomplishments;

  •  Drywall and taping complete on all walls,
  • Floor and wall tiling complete in restrooms,
  • Vestibule ready for drywall.

 Week 42 & 43 –Goal;

  • Complete all drywall for walls and ceiling,
  • Begin tiling of church floor,
  • Build Altar platform and ramps,
  • Begin work on parking lot.