Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 4

August 21 - August 27, 2016

As we begin the last week of demolition it seems like there’s not much left of our Church. In Week 4 we will remove the siding of the Bell Tower, remove and mitigate the asbestos in the tile floor of the body of the Church and begin grading of the parking lot. In week 5 we should be able to start building out the basement foundation.

Week 4 - Completed

• Sanctuary wall (east) has been completely removed down to the foundation.
• Removed Sanctuary platform.
• Removed radiators and boiler.
• Removed wall finishes down to brick in front entrance (Bath and Usher closet).

Week 5 - Goal

• Remove siding and vent panels from Bell Tower.
• Remove flooring from front entrance.
• Remove gas meter and cap line until new service is installed.
• Remove tile flooring in Church body and mitigate for asbestos.
• Begin grading for parking lot.