Week 37 was a VERY productive week. The flat roof has been sealed and completed and the floor in the addition was poured to bring it level with the existing floor. Ceiling framing is near completion in the addition as well as all framing and insulation on exterior walls. You can see that the window frames have been installed with the glazing (clear glass) to begin and continue into week 38. With the framing in; electrical, plumbing, HVAC and sprinkler systems can continue in the back area.

Week 38 will see drywall begin to go up, complete window installation and finish the stone on the patio.

See our Campaign Board in the Berst Hall lobby (East entrance) to see the latest pictures.

Week 37 – Completed

  • Insulation on exterior walls.
  • Wall and ceiling framing in addition.
  • Restroom plumbing.

Week 38 – Goal

  • Install floor in front lobby and begin dry walling.
  • Complete installation of exterior windows.
  • Stone back patio walls.