Rain continued into Week 36 but thankfully no snow.  A big milestone was the completion of the shingled roof with plans to seal the flat roof this weekend making the building water tight.  Work also began on building the ceiling in the addition as well as framing the Sacristy and restroom areas.

Week 37 should see the pouring of the floor in the    addition.  This pour of about 2 inches will bring the floor level with the old structure.  This too is a big milestone.

See our Campaign Board in the Berst Hall lobby (East entrance) to see the latest pictures.

Week 36 – Completed

  • Completed roof trusses over Altar.
  • Completed roof shingling and flat roof.
  • Begin framing attic “catwalk” and ceiling.

Week 37 – Goal

  • Begin work on parking lot (weather permitting).
  • Continue framing walls and ceiling.