Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 35

March 26 - April 1, 2017

WEEK 35

It was a very wet Week 35 which hampered progress. Work continues with installation of the fire suppression system and electrical, our mechanical (HVAC) is nearly complete and all exterior brick and stone facing is 90% complete.
 
A reminder...because of printing schedules, when you read this article it is a weekbehind. Visit our Building Campaign board in the front lobby to see the current status as well as a slideshow of pictures for the current week.
 
Week 35 – Completed
  • Connected to City Water. All utilities are now live
 
Week 36 – Goal
  • Complete roof trusses over Altar.
  • Complete roof shingling (weather permitting).
  • Begin framing attic catwalk and ceiling.
  • Begin work on parking lot (weather permitting).