CHURCH RENOVATION

PHOTOS - WEEK 33

March 12 - March 18, 2017

WEEK 33

Week 33 progress on was limited due to the wind, the cold and the SNOW!!  Work on the roof and outside in general was stopped but electrical and mechanical work continued in the basement and body of the Church.  As you can see the roof of the new addition was “decked” for the roofers to continue East which will begin in Week 34.  The roof over the South Confessional was also installed in anticipation of shingles next week.

See our Campaign Board in the Berst Hall lobby (East entrance) to see the latest pictures.

Week 33 – Completed

  • Roof decking on addition.
  • Roof installed on South Confessional.

Week 34 – Goal

  • Begin work on parking lot.
  • Begin interior wall framing.
  • Brick facing over Alter roof “gable”.
  • Pour patio floor.