WEEK 31

In week 31 it was all about Bricks and Beams. Despite Mother Nature reminding us that we are still in the winter season you can see a lot of progress on the brick facing. We also raised the steel joists in place in the addition. Week 32 will see us completing the brick and stone facing, begin decking the roof and pouring the Sacristy floor and patio.
See our Campaign Board in the Berst Hall lobby (East entrance) to see the latest pictures.

Week 31 – Completed

• Build out south Confessional with blocks / bricks.
• Continue brick facing.
• Finish steel joists installation on addition.

Week 32 – Goal
• Being installation of storm sewer for parking lot
• Seal roofing over Sacristy.
• Pour floor for Sacristy / Restroom section.
• Pour patio / ramps.

Click the Image Below for all the Photos from This Week.