Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 30

February 19 - February 25, 2017

WEEK 30

Week 30 was another very busy week.  The flat roof over the Sacristy and restrooms was set in place this week as well as the interior basement stairs.  As you can see the brick work is going up quickly and should be completed by the end of Week 32.  Something else on the outside you may have noticed is that the tower roof has been shingled and the Cross has been removed for inspection and measurements.  A new Cross will be installed.

The walls of the existing Church were stripped down to the brick exposing some interesting features.  Exhaust holes for flues from potbelly stoves can be seen on the north and south walls, brick arch work in the old choir loft and it looks like all was painted white. 

See our Campaign board in the Berst Hall lobby to see pictures of the bricks.

Week 30 – Completed

  • Remove interior wallpaper and plaster down to brick in existing Church.
  • Complete West and South block walls (back of building)
  • Place steel roof girders and roof deck for back section (Sacristy / Restrooms)
  • Complete North and South entrance steps to “Hobbit Doors”.
  • New shingles on Bell Tower roof.

Week 31 – Goal

  • Build out south Confessional with blocks / bricks.
  • Continue brick facing
  • Finish steel joists installation on addition.
  • Begin laying plywood sheathing for new roof.
  • Begin installation of storm sewers for parking lot.