Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 24

January 8 - January 14, 2017

WEEK 24

Week 24 was a very productive week.  The north wall has been completed with work beginning on the east wall (Altar) and the north corner of the church where the old meets the new.  By the end of Week 25 we should see the block walls complete.  We still have the back wall (east) to start but that is pending the completion of the footings.  This is the sacristy area which is directly behind the Altar wall as well as the restrooms which are at the NE corner of the new addition.  We also laid a ¾” subfloor on top of the existing floor.  On top of this will be tile, installed much later in the project. 

Another key milestone was the installation of the steel beam which will support the floor joists that will span from the old church floor to the new floor for the addition.  The picture above shows this beam which, as a point of reference, is where the steps to the altar were.

Week 24 – Completed

  • Mechanical begins HVAC installation.
  • New sub floor installed in body of church.
  • Steel columns and beam installed for transition floor.
  • Completed North wall.

Week 25 – Goal

  • Steel columns installed that will support main roof trusses.
  • Begin work on transition floor.
  • Complete block wall on east and west ends of addition.
  • Begin building Narthex wall.

Click the Image Below for all the Photos from This Week.