Week 23 was a short and bitter cold week.  Scaffolding was moved from the south wall to the north wall where they can assemble the north wall to match the south wall.  Temporary heating was setup in the basement and church. With the holidays behind us we can now get moving again. 

Week 24 will see a flurry of activity as we begin to install the HVAC equipment and ducts, begin electrical work and start the renovation work inside the church.  In addition block work will continue and work on the east foundation (sacristy and restrooms) will resume.

Week 23 – Completed

  • Installed temporary heat for basement and church
  • Move scaffolding to north wall, continued work on wall.
  • Steel ordered for addition and transition floor.

Week 24 – Goal

  • Mechanical on site to begin HVAC installation.
  • Electrical on site to begin electrical work.
  • Carpenters on site to begin work in front entrance of church
  • Steel columns delivered (4), floor columns (3), floor beam at transition
  • Resume foundation work at east end of addition