CHURCH RENOVATION

PHOTOS - WEEK 20

December 11 - December 17, 2016

WEEK 20

Old Man Winter paid a visit to Coal City in Week 20 causing a short work week.  But, we were able to get the footings poured and should be able to finish the foundation for the Sacristy and restroom area this week.  If the weather co-operates we should also see wall blocks going up on the south wall.

The picture above shows the scaffolding used to build the block walls setup at the SW addition corner.

Week 20 – Completed

  • Pour the footings and walls, with the proper weather protection in place, at the east end of the church for the footing and foundation that support the entire rear of the church.
  • Nicor Utility to return Gas meter to the new foundation and install gas line.
  • Setup expandable scaffolding for block work at SW corner of addition.

 Week 21 – Goal

  • Masonry will begin on the SW corner of the building with the block.
  • Mechanical contractor will start lay out and installation of the air handling units in the basement.
  • Fire sprinkler contractor to start in the existing structure.
  • Steel for the link between the two buildings installed.