Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 2

August 7 - August 13, 2016

Week 2 saw more “behind the scenes” work instead of physical work as was the goal. Scheduling and logistics, plan reviews, asbestos testing and permits were the main effort.  All necessary and now complete.  Some demolition work continued later in the week with the rest scheduled for Week 3.

It’s important to note that the Coal City Village Board waived $3,696.00 of our permit cost by a unanimous vote by the Board.   Thank you to the Coal City Village Board for your kind words in recognizing the community out-reach and support from our Church parishioners.

Week 1 - Completed

Construction permit received and posted; Plans reviewed and approved; Asbestos testing and mitigation; Remove “white” garage; Began demolition of the balcony

Week 2 - Goal

Finish removing balcony and stairs; Remove "hip" roof on east side of church; Remove Sanctuary wall (east); Remove Sanctuary platform; Remove confessional; Begin prepping parking lot area.  The plan is to build out the parking lot  including curbs, drainage and gravel in the next 2 months   Asphalt and striping will be applied at end of project.