Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 18

November 27 - December 3, 2016

WEEK 18

Week 18 was focused on installing the pre-cast flooring which began on Wednesday. Before that we finished the basement floor, exterior stairs and received all the HVAC equipment that will be installed in the basement. As we begin to see signs of winter close in our focus is to get the walls up in the next couple of weeks. Wall construction will be cinder blocks with exterior brick facing and metal framing inside. 

Week 18 - Completed

• Backfill and concrete area between church and addition.
• Exterior stairs to basement complete (north side).
• Basement floor complete.
• Installed pre-cast floor for new addition.
• Delivery of HVAC equipment in basement and outside units.

Week 19 – Goal

• Complete backfill around basement.
• Remove all remaining soil to off-site location.
• Delivery of blocks and begin building the walls.

Click the Image Below for all the Photos from This Week.