Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 17

November 20 - November 26, 2016

WEEK 17

Week 17 was a short week with the Thanksgiving holiday but much was done. The basement walls are all complete with the remainder of the floor to be poured in Week 18. Steel beams were also placed. These beams will support the new “pre-cast” floor. Week 18 should be a very busy week weather permitting. The pre-cast floor sections will be set in place, exterior stairs will be poured, back filling of the basement walls and we should see a delivery of the cinder blocks to be used to build up the walls.

Week 17 - Completed

• Basement walls complete including exterior stair well.
• Steel columns and beams installed.
• Sump and ejector pits completed.

Week 18 – Goal

• Complete exterior stairs.
• Pour the rest of the basement floor.
• Continue to backfill the perimeter of basement.
• Delivery and install pre-cast floor.
• Delivery of cinder blocks for walls.

Click the Image Below for all the Photos from This Week.