October 30 - November 5, 2016

WEEK 14

Progress is on the rise.  Basement walls are the focus for the next couple of weeks.  It looks like we will do 3 pours for the 11 foot walls with the 1st pour completed.   At the end of week 14 the West wall and half of the South wall were poured.  Week 15 will focus on finishing the South wall and then most of the East wall.

Week 14 - Completed

  • West wall and South wall (partial) completed

Week 15 – Goal

  • Set forms and pour for East wall and finish South wall
  • Begin setting forms and rebar for final pour or North wall.