Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 12

October 23 - October 29, 2016

WEEK 12

In Week 12 we finally started forming the footings for the addition. Water continues to be a challenge. Instead of setting the footing forms on dirt it was recommended that we dig out another 3-4 inches and lay in gravel under the footings. We also rolled out a mesh like material that will protect against hydro-static water pressure.

Week 12 - Completed

  • Continue forming addition footings.

Week 13 – Goal

  • Complete footings upon which we will set the forms for the basement walls.

Click the Image Below for all the Photos from This Week.