Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 11

October 9 - October 15, 2016

WEEK 11

In Week 11 we had to address the issue of shoring up the area around the new electric service transformer pad. Just east of the pad will be the outside basement staircase access. That’s when Wren Construction was engaged to evaluate and resolve the problem. Twelve foot long steel panels where “pushed” into the ground in an “L” shape, shoring up the Pad and NE corner of the Church.

With the “Big Dig” complete Week 12 will see us forming and pouring cement.

Week 11 - Completed

• Installed shoring in area for exterior basement stairs. Behind construction trailer.
• Basement dig is complete including construction access ramp

Week 12 – Goal

• Begin forming the foundation / basement area and pouring cement.

Click the Image Below for all the Photos from This Week.