Parish Center Progress - September 15, 2013

Return to Church Renovation Home Page

CHURCH RENOVATION

PHOTOS - WEEK 1

July 31 - August 6, 2016

Week 1 of our 35 week renovation project began on August 1, 2016.  This is a true milestone in the history of our Church.  The first 2 months will be in demolition and preparing for the foundation for the expansion as well as the new parking lot.

We will provide a weekly progress report in our bulletin but it’s important to note that due to the delay in preparing the bulletin and printing there will be a 2 week delay.  Meaning that when you read this it will be the weekend before Week 3.   So….what you read will not necessarily match with what you see.

Week 1 - Completed

  • Removed: Altar wall "skin" down to brick; Sacristy to ground level; Steps up to Altar "stage"; North and South chimney tops; North and South stairs and ramp; Front entrance concrete approach; Both interior walls and ceiling in front entrance (bath and usher room); Choir platform on balcony; Carpet from balcony and stairs, back area under balcony and entrance stair

Week 2 - Goal

  • Remove:  balcony and balcony stairs; carpet & flooring to sub-floor in body of church; Altar "stage"; "hip" roof on east side of church.  This roof is resting on the east wall that will be removed;  Altar wall; “white” garage.
  • Begin prepping parking lot area.  The plan is to build out the parking lot including curbs, drainage and gravel in the next 2 months Asphalt and striping will be applied at end of project.

 

Click the Image Below for all the Photos from This Week.